Certification Roadmap
Regulatory and voluntary certifications are acquired progressively across the site lifecycle. The timeline below is per-site: T0 is the site's Commercial Operation Date. Pre-COD certifications are prerequisites for startup; post-COD certifications build an operating record and expand the site's permitted service scope.
Pre-COD vs post-COD acquisition detail
- Pre-COD (T−24 to T0). The national environmental compliance authority review begins at design (T−24) and iterates to permit issuance. The Cat-1 operator license under the national waste-management regulation and the discharge/emissions permit from the national environmental regulator are issued during ASI SIT (System Integration Testing) at T−3 mo. The national standards body product certification begins per RC-grade product batch during SIT and continues per production batch thereafter.
- Post-COD (T0 → onwards). ISO 14001 / 45001 / 9001 are pursued within the first operating year, once continuous data supports the audit. The national sustainability initiative reporting participation begins at T0 and is ongoing. Third-party accredited analytical testing (PFAS / dioxin destruction-and-removal-efficiency audit) is scheduled during the first operating year and repeats periodically.
- Cat-2/3 HAZMAT expansion under the national waste-management regulation. Sites intending to accept HAZMAT-classified feedstock (e.g. asbestos for Glass MAX vitrification; PFAS-containing streams for CRSCU destruction service) apply for Category 2 or 3 expansion after building a Year-1 operating record. This is a per-site decision, not a default.
- Continuous obligations. CEMS reporting, the national environmental regulator's annual discharge-permit renewal, operator-condition compliance under the national waste-management regulation, and submissions to the national waste-tracking platform are ongoing post-COD. The audit-of-record cadence is defined in each site's operator license.
Carbotura's ACM technology sits at the DFM (Design for Manufacturability) / ERL (Engineering Readiness Level) framework — post-prototype, factory-fabricated production-grade modules. First-of-a-kind facility certifications require operating history; framework certifications (ISO management systems, third-party audit) are pursued in parallel and pre-COD where jurisdiction permits.
Engineering Detail
Certification program:
- ISO 9001 (quality management) — Carbotura, Inc. corporate — held or in progress at parent level.
- ISO 14001 (environmental management) — deployment-level, pre-COD or immediately post-COD per site.
- ISO 45001 (occupational health & safety) — deployment-level, per site.
- ISO 50001 (energy management) — deployment-level, where jurisdiction permits pre-COD.
- national/local-content certification — Carbotura's local entity holds national content certification at Phase 1.
- the national waste-management regulation — facility-level, per-site license under waste-management and industrial-licensing articles.
- Third-party independent reviewer — attestation of URVS 1.0 methodology commissioned at definitive-agreement execution (part of Carbotura's Urban Reserve Valuation Standard independent verification).
Actual certificates and audit reports (post-COD) available directly on issuance.